Scope of Project
- New building for year-round agricultural STEAM (Science, Tech, Engineering, Arts, and Math) programming
- 2400 square foot building includes large teaching space with learning lab and kitchen; offices and flushable restrooms
- Funded by a State of Illinois Museum Grant through IDNR
Concept Plan
Project Timeline
Completed; Dedication Ceremony held on September 28
Updates
Finished Facility on September 28, 2024
To see ribbon cutting picture and a photo slideshow: click here
Concrete floors poured the week of April 8, 2024
Walls went up the week of March 18, 2024
Girders were put up the week of February 12, 2024.
Foundation poured January 9, 2024.
Foundation footings poured January 5, 2024.